In a distributed photovoltaic power gridbid for specific processes, the project Owner of concern are:
1 project owners to help fill out the form
by the power companies, but the owners fill their own needs best understanding
of the content, while residents to apply for the owners as well as the need to
provide a copy of my ID card, household, real estate license and other
documents; owners of the best business consulting in advance to the grid, to
understand clearly.
(2) If the residents are occupied by the
owners of the project area of public space, but also need to provide the
applicant and where the unit of all households in writing signed certification
(including the signature of all participants, telephone number, ID number) and
where the residential property owners' committee proof of consent by the stamp
in their neighborhood communities.
3 When the power grid enterprise access
solutions prepared after completion, the project owner to inform as soon as
possible whether they can accept the power companies have raised objections as
early as possible, as this may affect the construction schedule.
4 before the construction of the project,
residents of the owners also need to prepare the right size photovoltaicpanels, it is best unified specifications, the same power, according to the
project capacity options matching inverter, inverter to the metering device
connection cable, installation support concrete barrier, tripod and other
infrastructure, and power companies will be provided free metering device.
6 project owners in completing the
application commissioning and acceptance of the application form, you can
request assistance in completing the grid enterprises.